Building Contractors
The one stop building solution

New Filling Station and Forecourt, Derwent Filling Station, Keswick

Category: Commercial

Construction of a new filling station, whilst the existing remained trading was always going to be a challenge. Construction of the steel framed structure, with local slate roof and stone walls, integrate the building into the surroundings. The retail space of the new building was increased twenty fold. Site remediation following a previous fuel leak added to the difficulty of turning the project round in a twenty week period. An example of the company’s successful progression into the commercial sector.

Client: R & L Properties
Completion: August 2009
Architect: Martin Cuthell Limited, Keswick
Value: £550,000
Size: 240m
Duration: 20 Weeks
Procurement: Negotiated contract

Sub Contractors

Structural steelwork
Slate Roofing
Mechanical and Electrical Installation
Suspended ceilings
Painting
Floor coverings
Forecourt electrical
Fuel Pump Installation
Groundworks
Road Markings

Back to Recent Projects